Scope of works
The Works are split into 3 specific areas as follows: • Enabling works – Installing sheet piling through earth and engineered dams both upstream and downstream of the river Frome to provide a robust temporary dam • Permanent works- Install sheet piling both East and West of M5 tying into concrete segregating wall , existing scour piles and existing riverbank. Install capping beam to top of all sheet piles. • Remedial works – Remove sheet piles from the temporary dam and remove from site.