Scope of works
The Contracting Authority wants to purchase the complete functional supply of a total of approximately 20 km 220 kV three-core submarine cable (installed as 3 separate, parallel cable systems) containing an optical fibre cable, including all labour, equipment and materials required for design, fabrication and factory testing, transport of cable and accessories to a port in Zealand, Denmark, installation of transition joints and hang offs and completion and commissioning as a part of a three new 220 kV cable system connecting Vordingborg Nord (VONØ) substation to Eskilstrup (ESK) and Nørre Radsted (NRA) substations. For further details concerning the purchase, reference is made to the tender documents.
- Type
- Contract award
- Contract Award
- Sector
- Electrical Equipment & Power Systems
- Procedure
- neg-w-call
- Classification
- 31321300, 31300000, 31340000, 31343000
- Original notice
- Sign in to open the original notice